CCGT – Latest Years Operating History
2014 / 135371 / 1980
2015 / 135914 / 2006
From June 2015: Plant officially closed. Preservation measures in place to ensure potential reutilization.


CCGT was built as the Flagship in the early 90s
• The plant was built under an EPC contract
• The whole plant was constructed using a modular approach with high level of prefabrication
• Robust and reliable V.94.2 generation family
• Equipped with by-pass stack (CCGT and OCGT operational modes possible). Very high flexibility and
rapidness in the respond.
CCGT – Latest Years Operating History
2014 / 135371 / 1980
2015 / 135914 / 2006
From June 2015: Plant officially closed. Preservation measures in place to ensure potential reutilization.


| Manufacturer | Siemens |
|---|---|
| Power Output (net) | 2 x 450 MW |
| Lay-out | 2 Modules of (2 GT + 1 HRSG + 1 STG) ea |
| Grid connection | 400 kV |
| Combined Cycle Mode Efficiency | 49,5 % |
| Open Cycle Mode Efficiency | 33,0 % |
| Total Surface (gross) | 10 Ha |